Question : 25 employees can finish work in 20 days. After how many days should 10 employees leave the job so that the work is finished in 30 days?

Option 1: 7 days

Option 2: 6 days

Option 3: 3 days

Option 4: 5 days


Team Careers360 16th Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: 5 days


Solution : Given, 25 employees can finish work in 20 days.
According to the question,
Total work = 25 × 20 = 500 units
Let us assume that 10 employees leave after $x$ days.
⇒ Work done in $x$ days = $25x$
Now, (25 – 10) = 15 employees work for (30 – $x$) days.
⇒ Work done in (30 – $x$) days = 15(30 – $x$)
According to the question,
⇒ $25x+15(30-x)=500$
⇒ $25x+450-15x=500$
⇒ $10x=500-450$
⇒ $10x=50$
⇒ $x=5$ days
Hence, the correct answer is 5 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books