Question : A can do a piece of work in 16 days. B can do the same work in 24 days. A started the work alone. After how many days should B join him, so that the work is finished in 10 days?

Option 1: 6 days

Option 2: 2 days

Option 3: 5 days

Option 4: 1 day


Team Careers360 16th Jan, 2024
Answer (1)
Team Careers360 18th Jan, 2024

Correct Answer: 1 day


Solution : 1 day's work of A $=\frac{1}{16}$
1 day's work of B $=\frac{1}{24}$
The work can be finished in 10 days.
Let $x$ be the day/days after which B joins A.
So, A works for 10 days and B for $(10-x)$ days.
According to the question,
$\frac{10}{16}+\frac{10-x}{24}=1$
⇒ $30+20-2x=48$
⇒ $x=1$
Hence, the correct answer is 1 day.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books