Question : If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same work in 70 days?
Option 1: 70
Option 2: 50
Option 3: 40
Option 4: 80
Correct Answer: 50
Solution :
The relation between men and the number of days is given by:
Where
According to the question,
∴ 50 men will be required to complete the work in 70 days.