Question : Riya alone can complete a piece of work in 6 days while Siya alone can do the same work in 9 days. If they both work together, then how many days will be required to finish the work?
Option 1: $\frac{45}{13}$
Option 2: $\frac{18}{5}$
Option 3: $\frac{33}{17}$
Option 4: $\frac{55}{16}$
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{18}{5}$
Solution : Given: Riya alone can complete a piece of work in 6 days while Siya alone can do the same work in 9 days. Let the total work = LCM of 6 and 9 = 54 units So, the efficiency of Riya = $\frac{54}{6}$ = 9, and the efficiency of Siya = $\frac{54}{9}$ = 6 Total efficiency = (9 + 6) = 15 So, together they will finish the work in $\frac{54}{15}$ = $\frac{18}{5}$ days Hence, the correct answer is $\frac{18}{5}$.
Answer Key | Cutoff | Selection Process | Preparation Tips | Eligibility | Application | Exam Pattern
Question : A alone can do a piece of work in 7 days, while B alone can do it in 10 days. In how many days will they complete the same work if they both work together?
Question : S alone can do a piece of work in 14 days. T alone can do the same work in 21 days. U alone can do the same work in 28 days. Working together, in how many days will they complete the work?
Question : A alone can complete a work in 16 days and B alone can complete the same work in 96 days. In how many days both A and B together can complete the same work?
Question : Avi alone can do a piece of work in 60 days while Prakash alone can do it in 80 days. In how many days will they finish it together?
Question : X alone can finish a work in 18 days, and Y alone can finish the same work in 9 days. If X, Y, and Z together can finish the same work in 4 days, then in how many days Z alone can finish the work?