Rudra Sanjay and tiger can complete a piece of work in 48 days 60 days and 72 days respectively they started the work together but after 9 days Tiger left if the Sanju live 6 days before the completing of the work in how many days will the work be completed


Simran 27th Mar, 2020
Answer (1)
Sai Sri Nandan Ch 27th Mar, 2020

Hello,

Let the work done by Rudra, Sanjay and Tiger in one day individually be x,y,z respectively.

Therefore, from question, 48x = 60y = 72z.   Let this be equation ((1)).

For initial 9 days, work done is 9(x+y+z).

Next 6 days, work done is 6(x+y).

The rest of the days, say M days, work done is M * x.

Adding all these, we get, (M+9+6)x + (9+6)y + 9z.

By using equation 1, convert this into only "x" terms.

Thus we get, (M+9+6+11.2+6)x. This work is equal to the total work, i.e 48x.

Thus, solving for M, we get, (M+32.2)x=48x

M=15.8. Rounded off, we get M = 16 days.

Therefore total days required is 16+9+6= 31 days.

Hope this helps.

Comment for clarification.

Thanks.

Related Questions

Amity University, Noida Law A...
Apply
700+ Campus placements at top national and global law firms, corporates and judiciaries
Amity University Noida B.Tech...
Apply
Among Top 30 National Universities for Engineering (NIRF 2024) | 30+ Specializations | AI Powered Learning & State-of-the-Art Facilities
Amity University Noida MBA Ad...
Apply
Amongst top 3% universities globally (QS Rankings) | Ranked among top 10 B-Schools in India by multiple publications
Amity University, Noida BBA A...
Apply
Ranked amongst top 3% universities globally (QS Rankings)
MAHE Online MBA
Apply
Apply for Online MBA from Manipal Academy of Higher Education (MAHE)
FLAME University | MBA 2026
Apply
NAAC A++ Grade | MBA program graded A** (National) by CRISIL | AACSB, ACBSP and BGA Member
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books