Question : A alone can do a work in 14 days. B alone can do the same work in 28 days. C alone can do the same work in 56 days. They started the work together and completed the work such that B was not working in the last 2 days and A did not work in the last 3 days. In how many days (total) was the work completed?
Option 1: $\frac{82}{7}$ days
Option 2: $\frac{79}{7}$ days
Option 3: $\frac{65}{7}$ days
Option 4: $\frac{72}{7}$ days
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: $\frac{72}{7}$ days
Solution : Given: A alone can do a work in 14 days. B alone can do the same work in 28 days. C alone can do the same work in 56 days. Use the formula, Total work = efficiency × time.
For the last 2 days, B has not worked, while A has not worked for the last 3 days. Let the entire work be finished in $x$ days. ⇒ $4(x–3)+2(x–2)+x=56$ ⇒ $4x–12+2x–4+x=56$ ⇒ $7x=56+16$ ⇒ $7x=72$ ⇒ $x=\frac{72}{7}$ days Hence, the correct answer is $\frac{72}{7}$ days.
Candidates can download this ebook to know all about SSC CGL.
Admit Card | Eligibility | Application | Selection Process | Preparation Tips | Result | Answer Key
Question : A can do $\frac{1}{3}$rd of a piece of work in 32 days, B can do $37 \frac{1}{2}$% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left and A joined C and together, completed the
Question : To do certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in _______ days.
Question : A alone can do $\frac{2}{5}$ of a work in 12 days. B is 25% more efficient than A. C alone can do the same work in 12 days less than B. D is 25% less efficient than C. If they all work together, then the work will be completed in how many days?
Question : A can do a piece of work in 9 days, while B can do it in 12 days. A and B together can do the work in:
Question : A alone can finish a work in 15 days. A works only for the first two days and the last two days. The rest work is done by B and the work is completed in 20 days. In how many days A and B together can finish the work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile