Hello Ashish,
Here is the solution of your question.I will be giving answers in 2 methods . One is long method and another one is short one.
Long Method:-
Rama's 1 day work will be = 1/8
Asha's 1 day work will be = 1/14
So, Rama and Asha together's work in 1 day = 1/8 + 1/14 = 11/56
So together they can complete work in 56/11 days .
Short Method:-(Trick)
Days required to work together = (8*14)/(8+14) = 56/11 days .
Hope you find the answers useful.