Mathews and Noel together can complete a piece of work in 63 days they started the work and after 27 days Mathews left and Noel complete the remaining work in 60 days in how many days Mathews complete the work


Simran 27th Mar, 2020
Answer (1)
ginnisachdeva02_9364270 Student Expert 27th Mar, 2020

Hi!

Solution of your query is given below :

Work done by matthews and Noel in 63 days =  [(1/63)*27]= 3/7

Remaining work =  1-3/7 =4/7

Now, 4/7 work is done by Noel in 60 days

Therefore, whole work will be done by Noel in 60*(7/4)= 105 days

Hope it helped to clear your delimma.


Related Questions

Amity University, Noida Law A...
Apply
700+ Campus placements at top national and global law firms, corporates and judiciaries
Amity University Noida B.Tech...
Apply
Among Top 30 National Universities for Engineering (NIRF 2024) | 30+ Specializations | AI Powered Learning & State-of-the-Art Facilities
Amity University Noida MBA Ad...
Apply
Amongst top 3% universities globally (QS Rankings) | Ranked among top 10 B-Schools in India by multiple publications
Amity University, Noida BBA A...
Apply
Ranked amongst top 3% universities globally (QS Rankings)
MAHE Online MBA
Apply
Apply for Online MBA from Manipal Academy of Higher Education (MAHE)
FLAME University | MBA 2026
Apply
NAAC A++ Grade | MBA program graded A** (National) by CRISIL | AACSB, ACBSP and BGA Member
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books