Mathews and Noel together can complete a piece of work in 63 days they started the work and after 27 days Mathews left and Noel complete the remaining work in 60 days in how many days Mathews complete the work


Simran 27th Mar, 2020
Answer (1)
ginnisachdeva02_9364270 Student Expert 27th Mar, 2020

Hi!

Solution of your query is given below :

Work done by matthews and Noel in 63 days =  [(1/63)*27]= 3/7

Remaining work =  1-3/7 =4/7

Now, 4/7 work is done by Noel in 60 days

Therefore, whole work will be done by Noel in 60*(7/4)= 105 days

Hope it helped to clear your delimma.


Related Questions

Chandigarh University Admissi...
Apply
Ranked #1 Among all Private Indian Universities in QS Asia Rankings 2025 | Scholarships worth 210 CR
TAPMI MBA 2025 | Technology M...
Apply
MBA Admission Open in Technology Management and AI & Data Science | NAAC A++ | Institution of Eminence | Assured Scholarships
Sanskriti University LLM Admi...
Apply
Best innovation and research-driven university of Uttar Pradesh
Maya Devi University LLM admi...
Apply
43.6 LPA Highest Package | 5.48 LPA Average Package | 150+ Courses in UG, PG, Ph.D
Amity University, Noida Law A...
Apply
700+ Campus placements at top national and global law firms, corporates, and judiciaries
Great Lakes PGPM & PGDM 2025
Apply
Admissions Open | Globally Recognized by AACSB (US) & AMBA (UK) | 17.3 LPA Avg. CTC for PGPM 2024 | Extended Application Deadline: 10th Feb 2024
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books